October 20, 2023

Metro C in Rome: the new construction site for the Piazza Venezia museum-station gets underway, update on traffic flow for pedestrians and vehicles

91% progress achieved on section t3 of the line from San Giovanni to Colosseo/ Fori Imperiali

 

  • 4,500 square metres for each of the 6 floors of the Piazza Venezia station
  • Work begins on the station foundations 
  • Coming in November the large “hydro-milling” machine for the construction of the station perimeter diaphragms 85 metres deep from street level
  • Project carried out by the Metro C consortium, led by Webuild and Vianini Lavori, with 400 people currently working on the line, and around 1,600 companies involved since the start of work

 

Rome, 20 October 2023 – A unique challenge, in terms of engineering, size, the importance of the historical-monumental context in which it is set, and its location in the heart of Rome, starts today with a new phase of work on the Piazza Venezia metro station of Line C of the Rome underground. The station, with a surface area of 4,500 square metres on each floor, will be a central hub of the entire Line C, the capital’s first self-driving underground line, commissioned by Roma Metropolitane and built by the Metro C S.c.p.a. consortium, led by Webuild and Vianini Lavori.

In the night between 20 and 21 October, with the installation of two traffic light systems, one on the Via del Corso side and one on the Piazza San Marco side, the new phase of the Piazza Venezia construction site will begin. The project envisages a two-way traffic system in the square, on the Palazzo delle Assicurazioni Generali side, and the provision of crossings to ensure the continuity of pedestrian and vehicle crossings.

 This new construction phase for the station foundations and reach a depth of approximately 85 metres, includes the installation of the system for the hydro-milling machine, consisting of a set of 14 silos of 50 cubic metres each. Site work, which has already begun in the central part of the square, will proceed with archaeological core drilling and soil pre-consolidation work, preparatory to the subsequent execution of the station diaphragms. The relocation of the interfering underground utilities will continue and, once the soils have been pre-treated, the installation of the hydro-mill is planned from mid-November. 

The construction of the Venezia station represents an infrastructural intervention of great engineering complexity. It will be developed on six underground levels and will have three entrances: Palazzo Venezia side, Auditoria di Adriano, and by the Vittoriano. The Venezia stations will be one of the so-called four archaeo-stations’ of Line C, together with San Giovanni, Porta Metronia and Colosseo/Fori Imperiali, designed to display the archaeological finds discovered during excavations. 

The T3 section, which is currently 91% complete, runs for 3 kilometres from the San Giovanni station (operational since 2018) to the Colosseo/Fori Imperiali station (under construction). It includes the Porta Metronia and Colosseo/Fori Imperiali stations, scheduled to open in 2025. To date, the work in progress employs about 400 people, including direct and third-party personnel, and involves a supply chain of about 1,600 companies since the start of the work. 

Line C will provide a sustainable and efficient connection between the centre and the suburbs, with positive effects on traffic levels and air quality. The work also represents a unique opportunity to safeguard archaeological treasures, creating new models for display and enjoyment of cultural heritage that otherwise would not be available to citizens and tourists. Line C will also be one of the most innovative metro lines in Italy, with driverless trains, remotely guided without drivers on board, similar to those used on the metro lines Webuild is building in Milan M4, and Riyadh.

Rome Metro - Line C, Venezia station - Webuild

Line C of the Rome Metro, Piazza Venezia Station
Metropolitana di Roma Linea C, Stazione Venezia: le fasi di realizzazione
Metropolitana di Roma, Linea C - Italia
1 / 0

Metro C in Rome: the new construction site for the Piazza Venezia museum-station gets underway, update on traffic flow for pedestrians and vehicles

Information material - Bridge project over the Strait of Messina
(*) Required information